Amrumbank West offshore wind farm | RWE
Amrumbank West offshore wind farm | RWE

Offshore wind farm off Heligoland has the capacity to supply up to 300,000 households with renewable energy

Amrumbank West offshore wind farm

The Amrumbank wind farm covers an area of approximately 32 km² and is located around 35 km north of the island of Heligoland and 37 km west of the North Frisian island of Amrum, inside the German Exclusive Economic Zone (EEZ). The distance from the nearest mainland coast is approximately 40 km. The offshore wind farm consists of 80 Siemens wind turbines with an installed capacity of 302 MW in total. This is enough power to supply around 300,000 households with renewable energy, saving 432,278 tonnes of CO2 emissions annually.

The turbines have a rotor diameter of 120 m (each rotor blade is 58.5 m long) and are situated in waters between 20 and 25 metres deep. The investment volume of the project was close to 1 billion euros.

Status: In operation

Facts & figures

00 kilometers

north of the island of Heligoland

00

Wind turbines

00 m

turbine height above sea level

Electricity for 00

households annually

00 MW

Installed capacity

00

Commissioning

Construction process overview

To prepare for the construction work on Amrumbank offshore wind farm, the research vessel Ice Beam carried out an analysis of soil samples from the seabed. After a 500-m safety zone was established around the planned outer locations of the WEA to secure the wind farm construction site, construction work started in May 2013.

The monopile steel foundations with a weight of between 80 and 300 tonnes each were driven into the seabed from January 2014. The large six-leg wind turbine installation vessel MPI Discovery, which RWE had chartered for the construction of the wind farm, was used to transport the elements from the port of Cuxhaven and erect them on site.

The first turbine was finally installed on 11 February 2015. The wind turbines were then commissioned one by one as the remaining turbines were erected. The first turbines went on stream in April 2015 and the complete wind farm was commissioned in October 2015.

Around 100 km of array cables were laid from the 80 wind turbines to the transformer station. An export cable transmits the power to the “HelWin beta” converter platform, which is 8 km away and transforms the three-phase alternating current (AC) from 155 kV to the ±320-kV level and converts it to direct current. The electricity is then transmitted through a submarine cable via high-voltage direct current transmission (HVDC “HelWin 2”) to the port town of Büsum, 85 km away, and from there another 45 km to the grid connection point at Brunsbüttel, where the electricity is converted back to three-phase alternating current (AC).

The wind farm is operated by Amrum-Offshore West GmbH, a 100 per cent subsidiary of RWE Offshore Wind GmbH. The service and operating station for the Amrumbank West offshore wind farm is located on Heligoland.


Location videos

Amrumbank project presentation


Impressions of the location

Amrumbank West offshore wind farm | RWE
Amrumbank West offshore wind farm | RWE
Amrumbank West offshore wind farm | RWE
Amrumbank West offshore wind farm | RWE
Maintenance work at night
Amrumbank West offshore wind farm | RWE
Amrumbank West offshore wind farm | RWE

You might also be interested in

Windpark Arkona

The wind farm has a capacity of 385 megawatts and can supply 400,000 households.

To the operating site

Offshore wind farm Kaskasi

Technological research in RWE's sixth wind farm off the German coast

To the offshore wind farm

Nordsee Ost offshore wind farm

Nordsee Ost is one of the largest commercial wind power projects off the German coast.

To the operating site

RWE Renewables Europe & Australia GmbH

RWE Platz 4
45141 Essen
Germany
+49(0)201-5179-5299