RWE Renewables GmbH

RWE completes installation of foundations and export cables at Triton Knoll offshore wind farm

RWE Image
  • Installation achieved within schedule, despite impact of Covid-19
  • 90 foundations and two 50 kilometre-long export cables now in position
  • Start of commercial operations at Triton Knoll expected in Q1/2022

Essen, 26 August 2020

Sven Utermöhlen | Chief Executive Officer (CEO) Offshore Wind

“With the installation of all foundations and the export cables, we have successfully completed a key offshore construction phase at Triton Knoll. The Triton Knoll team and our suppliers have shown a great commitment to reach this milestone within schedule, whilst coping with the many challenges posed by the Corona pandemic. We now look forward to installing the first 9.5 MW offshore turbines in early 2021. Throughout, the safety and welfare of everyone working on the project remains our top priority.”

Sven Utermöhlen, Chief Operating Officer Wind Offshore Global of RWE Renewables

RWE has taken a huge step towards first power generation in 2021 at Triton Knoll by completing the installation of all 90 turbine foundations and two 50-kilometre long export cables connecting offshore and onshore electrical systems. The successful installation was achieved during one of the project’s most challenging times due to the impact of Covid-19, and has been completed within the planned summer delivery window. With a commercial operation date expected in the first quarter 2022, Triton Knoll wind farm will have an installed capacity of 857megawatts (RWE’s pro rata share: 509 MW), capable of supplying green electricity equivalent to the annual demand of over 800,000 UK homes.

Triton Knoll offshore wind farm is located over 32 kilometres off the Lincolnshire coast. It is jointly owned by RWE (59%), J-Power (25%) and Kansai Electric Power (16%), with RWE leading the wind farm’s construction and long-term operation and maintenance works, on behalf of the project partners. Total planned investment volume amounts to approximately £2 billion. 

Triton Knoll was awarded a Contract for Difference (CfD) by the UK Department for Business, Energy & Industrial Strategy in September 2017. A Power Purchase Agreement (PPA) with Ørsted, under which the company will offtake 100% of the power produced by the wind farm, complements Triton Knoll’s CfD, mitigating any market price uncertainty for the first 15 years of the wind farm’s operation.

RWE is the second biggest player in offshore wind globally with ambitious plans for further growth

RWE has significant experience in the UK offshore market with nine wind farms in operation. Further offshore development projects, like the 1.4 GW Sofia offshore wind farm – 100% owned by RWE – underline the growth ambitions of the company in this country.

Tom Glover, RWE Renewables Chief Commercial Officer and RWE UK Country Chair said: “The UK is one of the most important markets for RWE, where we have significant growth ambitions in offshore wind. Following in the footsteps of Triton Knoll will be our 1.4 GW Sofia offshore wind farm, which has a potential investment value of around £3 billion. We are also looking forward to developing a number of extension projects to our existing UK offshore wind farms, in connection with opportunities arising from The Crown Estate’s latest leasing round.”

In addition to the UK, RWE's focus for offshore growth is on further core markets in Europe as well as in the Americas and the Asia-Pacific region. In Germany the company is currently building its Kaskasi offshore wind farm (342 MW, 100% RWE). RWE’s development pipeline consists of offshore opportunities with about 7 GW – not including central tenders, which the company is considering on top. 

For more information about the Triton Knoll offshore project, please visit: www.tritonknoll.co.uk 

 
RWE Image

Construction starts in Rhenish lignite area – RWE builds Aldenhoven wind farm

15.04.2024

Read more

RWE starts work on onshore cables as next step in construction of Thor Offshore Wind Farm

15.04.2024

Read more

More green electricity: RWE connects Lengerich wind turbine to grid after successful repowering

10.04.2024

Read more