Uw instellingen voor cookies en pixels op group.rwe

Selecteer welke cookies en pixels wij mogen gebruiken. Let op dat sommige cookies om technische redenen noodzakelijk en ingeschakeld moeten zijn voor een werkende website. Als u gebruik wilt maken van elke dienst op onze website, moet elke cookiecategorie geselecteerd zijn. Meer informatie vindt u in ons gegevensprivacyverklaring.

    • Behouden de stabiliteit van de website.
    • Slaan uw gegevens voor aanmelden op.
    • Zorgen voor een verbetering van de gebruikerservaring.
    • Leveren advertenties die bij uw interesses passen.
    • Zorgen ervoor dat u interessante inhoud direct op uw socialmedia-netwerk kunt delen.

U kunt uw cookie- en pixelinstellingen op group.rwe te allen tijde aanpassen via ons gegevensprivacyverklaring.

Wettelijke mededeling

Meer informatie
Alles selecteren Bevestigen

Wind farm Arkona - Largest wind farm of the entire Baltic Sea

The wind farm has the capacity to supply 400,000 households with renewable energy

Facts and figures

Wind farm location 35km northeast of the island Rügen
Commissioned in 2019
Electrical output (gross) 385 MW
Number of units 60 turbines
Turbine height 102m

The Arkona wind farm is located 35 kilometers northeast of the island of Rügen. The wind farm has a capacity of 385 megawatts and can supply approximately 400,000 households with renewable energy. The investment volume amounts to €1.2 billion. Compared to conventionally generated electricity, Arkona saves up to 1.2 million tons of CO2 annually. 60 turbines of the six-megawatt class from Siemens were installed. Arkona is a joint venture.

The partner companies were able to connect the Arkona offshore wind farm to the grid on time and at lower costs than originally calculated. It took only one year from the first ramming to the first electricity feed-in. Rarely before has an offshore project been completed so quickly. The reasons for the success of the fast completion are the detailed planning and the professionally implemented construction process. This is accompanied by the close cooperation with 50Hertz and the precisely coordinated partial feed-in option into the German extra-high voltage grid, which was made possible by the transmission grid operator before the connection was completed. After initially only the first of 60 turbines went online, further wind turbines were put into operation step by step. The transformer station and all 60 foundation foundations including connecting pieces were installed ahead of schedule. The internal parking cabling for connecting the turbines to the substation was also installed  before planned. Then towers, turbines and rotors were installed on the high seas.

In August, together with the first power supply, the Arkona electric offshore substation was also put under voltage. RWE, Equinor and the transmission grid operator 50Hertz share the platform. The optimal timing and technical coordination of the companies is helping to optimise offshore grid connection costs and speed up the energy turnaround.

Setting the pace was already achieved during construction: all 60 steel foundations of the wind farm were sprayed with a special anti-corrosion coating. During the 25-year operating period of the wind farm, several hundred tons less aluminum and other environmentally harmful substances are released.